CASE STUDY, RESIDENTIAL
Full height sheeted scaffold with fire retardant netting, on a building with water on one side
Pinnacle Scaffolding provided full height access to an apartment block on the water at Brentford in west London, covering the elevation that faces the dock. The building runs to several storeys and the scaffold was taken across the whole face and sheeted.
Two things made this job different from a standard block. The water, which decides where you can stand a scaffold and where you can land material. And the netting, because the client asked for fire retardant rather than standard and that is a request worth saying yes to without debate.
A waterside building takes one of your options away. On a normal block you can usually work the perimeter, bring material round to whichever side suits, and set the base out wherever the ground is best. Here the dock sits hard against one elevation, with moored vessels and a tidal foreshore below, so everything has to come in and go out from the land side.

That narrows the ground available for the base at exactly the point where the scaffold is carrying the most load, because a sheeted elevation of that height puts a serious amount of wind load back down through the structure.
The block was occupied throughout, so residents were coming and going underneath the works for the duration.
The client asked for fire retardant netting rather than standard debris netting. You can see it in the photograph below: the coloured tracer threads woven through the mesh are what tell you, on site and at a glance, that the netting on a scaffold is the treated kind rather than the ordinary kind.

It costs more than standard netting and it is not always specified. On an occupied residential block of this height it is a sensible ask, and when a client raises it we fit it rather than arguing the point.
Pinnacle set out a loaded base structure sized for the restricted waterside footprint, then took an independent scaffold up the full height of the dock elevation with boarded working lifts and toe boards at every level. The sheeting and the fire retardant netting went on across the whole face.
RAMS and method statements were provided as standard and every operative on site held a current CISRS card.
Managing a block with residents staying put through the works? Call 07879 118 423 and we will look at access and phasing before anything is priced.
KEY CREDENTIALS
It is debris netting treated so it resists ignition and does not carry flame up the scaffold. You can tell it apart from standard netting by the coloured tracer threads woven through it. It is specified on occupied residential blocks, on buildings with a hot works programme, and wherever a client or an insurer wants the extra margin. On this job the client asked for it and we fitted it.
Yes, but the base takes the planning rather than the lift heights. A waterside elevation limits where you can stand a scaffold and where material can be landed, so the loaded base structure has to be set out to work within the ground you actually have rather than the ground a standard drawing assumes.
No. Most of our residential block work is on occupied buildings. Access routes stay open, operatives work to sensible hours, and anything that changes a resident's normal route gets flagged before it happens rather than on the morning it happens.
Occupied apartment blocks are a regular part of what we do across London and the counties around it. The buildings vary, the constraints vary, and the only way to price one properly is to walk it first and find out what the ground, the access and the client's own requirements actually are.
Our London scaffolding page covers the rest of what we do across the capital.
If you manage a residential block with external works coming up, call us on 07879 118 423 for a free site survey.