A scaffold to a standard semi for roof, chimney or loft work usually goes up in under a day, and often in a morning. Getting to that day is the slower part: expect a site visit within 24 to 48 hours of first contact, and erection within 24 to 48 hours of a confirmed order. Where the scaffold sits on a pavement, the council licence decides your start date, not the scaffolder.
Written by the Pinnacle Scaffolding team, CISRS accredited scaffolders working across London, Kent, Essex and Surrey. Updated November 2026.
The three things that set your dates
Skip to
These are the shapes of job we do most often. Every one varies with the building, so treat them as the pattern rather than a promise.
| Job | Typical erection |
|---|---|
| Single elevation, two storey semi | Often a morning |
| Chimney access on a terrace | Usually a day, because it runs full height |
| Full wrap, detached house | A day, sometimes two |
| Scaffold with a temporary roof over it | Longer, the roof is a second structure |
| Blocks of flats and commercial frontages | Phased over several days, worked around occupants |
People assume the delay is the scaffolder's diary. Usually it is not. For standard residential work we can normally get a surveyor out within 24 to 48 hours of your first call, and get the scaffold up within 24 to 48 hours of you confirming the order. For urgent jobs, emergency roof access after storm damage being the common one, we can often attend the same day.
The thing that moves a start date is a pavement licence. Where any part of the scaffold sits on a pavement or a road, the scaffold needs a licence from the local highway authority under section 169 of the Highways Act 1980, and the application has a processing time. We submit it as part of the job, but once it is in, the council's lead time governs when the scaffold can legally go up. On a terraced street with no front garden that is effectively routine, and we build it into the booking rather than discovering it late.
On your own land, a scaffold can stay as long as the works need it. There is no general time limit, provided it is inspected properly and nothing about it has changed without being checked. Roof replacements, render work and anything weather dependent routinely run for weeks.
What does expire is a licence. A pavement or highway licence is issued for a set period, and if the job overruns it has to be extended before it lapses. That is worth knowing at the planning stage rather than in week six, because an expired licence stops the job rather than slows it.
Working to a date? Tell us what it is. We survey within 24 to 48 hours and will say straight away whether a licence puts your start at risk.
Tell us every trade that needs height access on that building and we will set the hire period once, properly, rather than you paying to erect it twice.
The expensive mistake is booking the scaffold around one trade and then discovering a second trade needed it too. If the roofer finishes and the scaffold comes down, and the decorator then wants the same elevations, you pay to erect it twice.
Before you book, work out everyone who needs height access on that building. Roof, chimney, guttering, fascias, rendering, painting, window replacement and solar panels can often share one scaffold if the programme is sequenced. That single decision saves more money than anything you will negotiate on the price.
It also helps to be realistic about weather. Roofing and rendering both stop in the wrong conditions, and a hire period set for a perfect fortnight in February will overrun.

A wagon arrives and the tube, boards and fittings come off at the kerb or on the drive. That is the noisiest part and it is over in the first half hour. The gang then sets the base, works up in lifts, boards each platform out, fits guard rails and toe boards, and ties the scaffold into the building as it rises.
Before anybody uses it, the scaffold is inspected and a handover is issued. If your roofer turns up and there is no tag or paperwork on it, that is worth a phone call rather than a shrug.
Three things help on the morning. Clear the elevation of bins, pots, furniture and anything you would rather was not stood on. Move cars off the drive if the wagon needs it. And tell us about a cat flap, a dog, a gate code or a side gate that is locked, because the gang will need to get to the back and nobody wants to be stood waiting while you are at work.
A scaffold against the front of your house changes two practical things. It gives anybody a route to your upstairs windows, and it takes light out of the rooms behind it, particularly if the scaffold is sheeted or netted.
On security, lock upstairs windows the way you would lock the front door, and tell your insurer the scaffold is there. Most policies are untroubled by it but a few want to know, and the time to find that out is before the works, not after an incident. Where a property is empty or the scaffold stands for a long run, anti climb measures at ground level are worth asking about at the survey.
On light, sheeting is the thing that darkens a room, not the scaffold itself. Sheeting goes on for a reason, usually to contain dust or to let a trade work in poor weather, so it is worth asking whether your job needs it or whether open tube will do. If it does need sheeting, knowing in advance beats finding out on the Monday.
If you have a date you are working to, tell us at the first call rather than at the end. Most of what delays a scaffold is foreseeable, and nearly all of it is easier to solve three weeks out than three days out.
The pricing guide covers what the hire period does to the figure, and the temporary roofs page explains the jobs where the scaffold has to keep the weather out as well as hold people up. You can also see real jobs we have done or check the towns we cover.
The part of your start date we do not control is the council, and councils are not alike. In Essex the application can only come from a licensed contractor. Across south east London it is borough by borough. Kent and Surrey each run their own. Start from the county page that covers you, or check the areas we cover list for your town.